INTRODUCTION: This outline is a general explanation of mechanic’s
lien laws. We hope it will help you understand the technical subject of mechanic’s liens. However, it is not a complete guide to all
of the problems and complications that might arise, and it should not be relied upon for specific legal advice.
DIFFERENCES BETWEEN GENERAL CONTRACTORS AND SUBCONTRACTORS: Under the
Mechanic’s Lien laws, there are very substantial differences between a Contractor and a Subcontractor.
-
A Contractor, or “general contractor,” is someone who has a contract
directly with the owner of the property, or with someone “knowingly permitted” by the owner to improve the real estate. Determining
who is the owner or “knowingly permitted” by the owner is discussed in more detail below.
-
A Subcontractor is someone hired by the “general contractor,” rather than
the owner, or the owner’s agent. Thus, the agreement to do the work is never made directly between the subcontractor and the owner.
All subcontractors should be aware that their lien rights are totally dependent on the contract between the owner and the general
contractor. If the general contractor does not have a contract with the owner or a person “knowingly permitted” by the owner to make
the improvements, or if the contract between the general contractor and the owner contains a clause that mechanic’s liens may not
attach to the property, then the subcontractor will not be able to have a lien.
III. STEPS REQUIRED OF A GENERAL CONTRACTOR TO ESTABLISH A MECHANIC’S LIEN:
The requirements that must be met by a general contractor to establish a mechanic’s lien are as
follows:
-
A valid contract: There must be a valid contractor for performance
of the work. Although the contract can be verbal, it is always better practice to have a written contract, with a complete list of
all work to be performed, and all of the terms of the contract clearly stated.
-
The contract must be with the owner, or with someone “knowingly permitted” by the owner: The
contractor should determine at the outset whether the person engaging his services is the owner of the
real estate, or is knowingly permitted by the owner to make improvements. The best practice is to determine (by a current title
commitment or title search) the identity of the owner of the real estate, and require the owner to join in the construction contract.
If the person entering into the contract is not the record owner of the property, then his authority to enter into the contract must be
determined. The following rules apply:
-
Land Trusts: If the property is held in a land trust, the
trustee should sign the contract, or the contractor should get a statement from the land trustee disclosing the names of the
beneficiaries, and the beneficiaries should sign the contract.
-
Landlords and Contract Sellers: The “owner” of rented property is the
landlord, and the “record owner” of property being sold under a land contract is the contract seller. Most leases and land contracts
forbid the tenant or buyer from making improvements which would create mechanic’s liens. Therefore, the contractor should require the
landlord or contract seller to consent in writing to the contract on rented property, or property being sold under a land contract.
-
Real Estate Developers: Often the developer is not the owner of the
land. The contractor should require that the owner consent in writing to the contract.
-
Married Persons: Where one spouse (i.e., the wife) holds title to the
property, and the other spouse (i.e., the husband) enters into the construction contract, the contractor claiming a mechanic’s lien
would have to prove that the spouse holding title knowingly permitted the other spouse to make the improvements. It is therefore best
to require both spouses to sign the contract.
-
The contractor must furnish materials or services: The types of
“materials or services” which must be furnished to create a contractor’s lien are specifically described in the mechanic’s lien statute.
The statute is very detailed, and almost all types of materials or services used in construction are included.
-
Performance of the contract: The contractor must complete work under
the contract, or show a valid excuse for non performance.
-
Sworn Contractor’s Affidavit: The contractor is not entitled to be
paid unless and until he gives the owner a sworn contractor’s statement, and a Notice about subcontractors. Therefore, this step
is crucial to both your right to be paid, and your right to claim a mechanic’s lien.
-
Record the lien claim: The contractor must record with the Recorder
in the county where the property is located, an “Original Contractor’s Claim for Lien” within four (4) months after the final work was
completed. (However, a lien claim recorded within two (2) years is still valid against the owner, but not other creditors.) If not
paid sooner, the contractor must also file a lawsuit to foreclose the lien within two (2) years from the completion of the work.
These are generally the steps that a “general contractor” must follow in order to establish and preserve his mechanic’s lien claim. As
stated above, however, these laws are extremely technical, and it is very easy to make serious mistakes.
IV. STEPS REQUIRED OF A SUBCONTRACTOR TO ESTABLISH A MECHANIC’S LIEN:
The requirements that must be met by a subcontractor to establish a mechanic’s lien are:
-
There must be a valid contract between the general contractor and the owner of the property, or someone “knowingly permitted” by
the owner to make improvements. Since the right of a subcontractor to claim a lien depends on the contract between the owner and the
general contractor, the subcontractor should be aware that the general contractor must have a contract with the owner, or someone
“knowingly permitted” by the owner to make improvements (discussed above).
-
The subcontractor must have a contract with the original contractor. Again, although a verbal contract may be acceptable, it is much
better to have a written contract, with all the terms clearly stated.
-
The subcontractor must furnish certain materials or services. Almost any type of materials or services used in the construction
industry is included.
-
The subcontractor must complete the contract, or have a valid excuse, beyond his control, for not completing the work.
-
Finally, the subcontractor must serve, and file, notice of his claim for lien as described below:
-
FOR EXISTING, OWNER-OCCUPIED, SINGLE FAMILY RESIDENCE: The
subcontractor must notify the occupant owner by certified mail, return receipt requested, addressed to the occupant owner at his
residence, WITHIN 14 DAYS FROM HIS FIRST FURNISHING MATERIALS OR LABOR, that he is supplying materials or labor. The notice must state
the name and address of the subcontractor (or material supplier), the date he first performed labor or services or furnished materials,
the type of work done or to be done (or materials delivered or to be delivered), and the name of the contractor who hired him. The
notice must contain the following warning in bold type:
NOTICE TO OWNER
Do not pay the Contractor for this work or material delivered unless you have received from the Contractor a waiver of lien by, or
other satisfactory evidence of payment to, the Subcontractor or Materialman.
-
90 DAY NOTICE OF SUBCONTRACTOR’S LIEN: A subcontractor must
serve the owner with a written notice of his claim within ninety (90) days after the date of completion of his work. This notice must
be served on the owner of record (as shown in the Recorder’s Office), or on the owner’s architect, agent or superintendent; and it must
be served either in person, or sent by “Registered or Certified Mail, with Return Receipt Requested, and delivery limited to addressee
only....” The notice must also contain the “Notice to Owner” language discussed above.
-
SERVICE ON LENDING INSTITUTION: The “Notice” must also be
served on lenders with mortgages on the property.
-
Record Claim for Lien: Within four (4) months after completion
of work, the subcontractor must record a claim for lien in the Recorder’s Office of the county where the land is located. He does not
have to wait until he has completed his work, but he must first serve a “Notice of Claim” on the owner and the lending agency, as set
forth above, and wait ten (10) days after that service.
-
File Suit Within Two Years: If still not paid, the
subcontractor must file suit within two (2) years after he has completed his work.
V. LIEN WAIVERS: A contractor or subcontractor can lose his
mechanic’s lien if he signs a lien waiver before being paid, so be very careful about signing lien waivers.
VI. EXTRAS: Extras, or work in addition to the contract,
should always be in writing, so that there is no question later about whether the “extra” was actually work to be performed under the
first contract. Extras should be specifically designated as “extras to the contract dated ____________,” so that the extra is not
treated as a separate, new contract. This is important for at least two reasons. First, two separate lien claims would be necessary
if the extra is treated as a separate contract. Second, the time for filing the Notice of Lien begins to run when work is completed
under the contract; if the “extra” is not part of the first contract, the time for filing the Notice of Lien on the first contract would
begin to run without regard to when the work is performed on the “extra.” For these reasons, it is best to have written extras
specifically referred to as “extras” to the contract.
VII. “NO LIEN” CLAUSES IN CONTRACTS: If the contract between the
owner and original contractor says: “No lien or claim may be filed or maintained by anyone...,” then no one can have a mechanic’s lien
on that particular job (with a few limited exceptions).
VIII. FORECLOSURE SALE: If the real estate is ultimately sold at a
foreclosure sale, the sales proceeds will be distributed to the creditors according to very technical and complicated rules.
IX. CONCLUSION: THIS DOCUMENT IS INTENDED ONLY AS A GENERAL GUIDE
TO MECHANIC’S LIENS, IN ORDER TO FAMILIARIZE CONTRACTORS AND SUBCONTRACTORS WITH THE BASIC PROVISIONS OF THE LAW. BECAUSE THE
MECHANIC’S LIEN LAWS ARE VERY TECHNICAL, AND THERE ARE EXCEPTIONS TO ALL RULES, ANY SPECIFIC LEGAL ISSUES SHOULD ONLY BE HANDLED BY A
COMPETENT ATTORNEY.
DATE: May 15, 1992.
Click Here to view in PDF format
NOTICE
This web page and the information contained herein may constitute advertising material under
the Illinois Rules of Professional Conduct.
The firm brochures provided by Smith, Landmeier & Elders, P.C. are intended to provide
general information on various areas of the law. They are not to be relied upon for specific legal
advice. Transmission or receipt of this information is not intended to create an attorney-client
relationship. Any specific legal questions or issues should be handled by a competent attorney.
Return to Home Page