Attorneys: Smith Landmeier & Elders, PC

15 N. Second St., Geneva, Illinois

MECHANIC'S LIENS:

AN EXPLANATION OF THE LAW OF MECHANIC'S LIENS

FOR CONTRACTORS AND SUBCONTRACTORS


INTRODUCTION:  This outline is a general explanation of mechanic’s lien laws. We hope it will help you understand the technical subject of mechanic’s liens. However, it is not a complete guide to all of the problems and complications that might arise, and it should not be relied upon for specific legal advice.

DIFFERENCES BETWEEN GENERAL CONTRACTORS AND SUBCONTRACTORS:  Under the Mechanic’s Lien laws, there are very substantial differences between a Contractor and a Subcontractor. All subcontractors should be aware that their lien rights are totally dependent on the contract between the owner and the general contractor. If the general contractor does not have a contract with the owner or a person “knowingly permitted” by the owner to make the improvements, or if the contract between the general contractor and the owner contains a clause that mechanic’s liens may not attach to the property, then the subcontractor will not be able to have a lien.


III. STEPS REQUIRED OF A GENERAL CONTRACTOR TO ESTABLISH A MECHANIC’S LIEN:   The requirements that must be met by a general contractor to establish a mechanic’s lien are as follows: These are generally the steps that a “general contractor” must follow in order to establish and preserve his mechanic’s lien claim. As stated above, however, these laws are extremely technical, and it is very easy to make serious mistakes.


IV. STEPS REQUIRED OF A SUBCONTRACTOR TO ESTABLISH A MECHANIC’S LIEN:   The requirements that must be met by a subcontractor to establish a mechanic’s lien are:

V. LIEN WAIVERS:  A contractor or subcontractor can lose his mechanic’s lien if he signs a lien waiver before being paid, so be very careful about signing lien waivers.

VI. EXTRAS:   Extras, or work in addition to the contract, should always be in writing, so that there is no question later about whether the “extra” was actually work to be performed under the first contract. Extras should be specifically designated as “extras to the contract dated ____________,” so that the extra is not treated as a separate, new contract. This is important for at least two reasons. First, two separate lien claims would be necessary if the extra is treated as a separate contract. Second, the time for filing the Notice of Lien begins to run when work is completed under the contract; if the “extra” is not part of the first contract, the time for filing the Notice of Lien on the first contract would begin to run without regard to when the work is performed on the “extra.” For these reasons, it is best to have written extras specifically referred to as “extras” to the contract.

VII. “NO LIEN” CLAUSES IN CONTRACTS:  If the contract between the owner and original contractor says: “No lien or claim may be filed or maintained by anyone...,” then no one can have a mechanic’s lien on that particular job (with a few limited exceptions).

VIII. FORECLOSURE SALE:  If the real estate is ultimately sold at a foreclosure sale, the sales proceeds will be distributed to the creditors according to very technical and complicated rules.

IX. CONCLUSION:  THIS DOCUMENT IS INTENDED ONLY AS A GENERAL GUIDE TO MECHANIC’S LIENS, IN ORDER TO FAMILIARIZE CONTRACTORS AND SUBCONTRACTORS WITH THE BASIC PROVISIONS OF THE LAW. BECAUSE THE MECHANIC’S LIEN LAWS ARE VERY TECHNICAL, AND THERE ARE EXCEPTIONS TO ALL RULES, ANY SPECIFIC LEGAL ISSUES SHOULD ONLY BE HANDLED BY A COMPETENT ATTORNEY. DATE: May 15, 1992.

Click Here to view in PDF format



NOTICE

This web page and the information contained herein may constitute advertising material under the Illinois Rules of Professional Conduct.

The firm brochures provided by Smith, Landmeier & Elders, P.C. are intended to provide general information on various areas of the law. They are not to be relied upon for specific legal advice. Transmission or receipt of this information is not intended to create an attorney-client relationship. Any specific legal questions or issues should be handled by a competent attorney.


Return to Home Page

Return to Client Brochures

Last Updated June 2, 2004